During the Change phase, when can a change project be created in the quality system?
The correct answer is D. Only after the previous change has been imported to the productive system. See the full explanation below for the reasoning.
Question
During the Change phase, when can a change project be created in the quality system?
Options
- AOnly after testing
- BOnly when the data is archived
- COnly when the starter system has been deleted
- DOnly after the previous change has been imported to the productive system
How the community answered
(21 responses)- A14% (3)
- B5% (1)
- C5% (1)
- D76% (16)