You upgrade an SAP HANA 1.0 system to SAP HANA 2.0. Which of the following activities are required to avoid compatibility issues after the upgrade. Note: There are 2 correct answers.
The correct answer is B. Delete all Backup schedules with the SAP HANA cockpit 1.0 C. Create new backup schedules after the upgrade. See the full explanation below for the reasoning.
Question
You upgrade an SAP HANA 1.0 system to SAP HANA 2.0. Which of the following activities are required to avoid compatibility issues after the upgrade. Note: There are 2 correct answers.
Options
- AExport the backup jobs history from SAP HANA 1.0 and import the history after the upgrade
- BDelete all Backup schedules with the SAP HANA cockpit 1.0
- CCreate new backup schedules after the upgrade
- DConvert all SAP HANA 1.0 backup schedules to SAP HANA 2.0 backup schedules
How the community answered
(38 responses)- A5% (2)
- B82% (31)
- D13% (5)
Community Discussion