Question
What is the correct sequence of the following four steps in the restart of the SAP HANA database system? Please choose the correct answer.
Options
- AAborted transactions are rolled back. 2. Open transactions are recovered. 3. Row tables are
- BAborted transactions are rolled back.
- CRow tables are loaded into memory. 3. Open transactions are recovered. 4. Column tables are
- DRow tables are loaded into memory. 2. Column tables are loaded. 3. Open transactions are
- ERow tables are loaded into memory. 2. Open transactions are recovered. 3. Aborted transactions