SAP
C_HANATEC142 · Question #86
Which of the following would you use to upgrade an SAP HANA system and keep the downtime to a minimum? Please choose the correct answer.
The correct answer is D. System replication. See the full explanation below for the reasoning.
Question
Which of the following would you use to upgrade an SAP HANA system and keep the downtime to a minimum? Please choose the correct answer.
Options
- AHigh availability
- BStorage replication
- CPartitioning
- DSystem replication
How the community answered
(53 responses)- A6% (3)
- B11% (6)
- C2% (1)
- D81% (43)
Community Discussion
No community discussion yet for this question.