Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)? There are 2 correct answers to this question. Choose:
The correct answer is A. Copy the data and log volume files from system B to system A. D. Restore a complete database backup from system B to system A. See the full explanation below for the reasoning.
Question
Which of the following steps allow you to create a test system (system A) based on a productive SAP HANA standalone system (system B)? There are 2 correct answers to this question. Choose:
Options
- ACopy the data and log volume files from system B to system A.
- BCopy a snapshot from system B to system A.
- CExport the data from system B to a file share and import the data to system A.
- DRestore a complete database backup from system B to system A.
How the community answered
(24 responses)- A75% (18)
- B17% (4)
- C8% (2)
Community Discussion