SAP
C_ACTIVATE12 · Question #73
Which of the following tasks are required in the Prepare Phase? There are 3 correct answers to this question. Response:
The correct answer is A. Train the project team B. Set up the infrastructure to support the project E. Identify relevant SAP Best Practices. See the full explanation below for the reasoning.
Question
Which of the following tasks are required in the Prepare Phase? There are 3 correct answers to this question. Response:
Options
- ATrain the project team
- BSet up the infrastructure to support the project
- CDefine the communication plan
- DApprove the test strategy
- EIdentify relevant SAP Best Practices
How the community answered
(34 responses)- A76% (26)
- C6% (2)
- D18% (6)
Community Discussion
No community discussion yet for this question.