Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?
The correct answer is A. User stories are in a ready state for NO more than the first three sprints. See the full explanation below for the reasoning.
Question
Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?
Options
- AUser stories are in a ready state for NO more than the first three sprints
- BProject scope and planning are completed and final
- CTimelines of the sprint may differ due to the workload
- DGo-live scope is fixed on the first of January the following year
How the community answered
(35 responses)- A77% (27)
- B6% (2)
- C14% (5)
- D3% (1)