In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.
The correct answer is A. DEV C. QAS. See the full explanation below for the reasoning.
Question
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.
Options
- ADEV
- BP-system
- CQAS
- DStarter system
How the community answered
(64 responses)- A77% (49)
- B17% (11)
- D6% (4)