C_ACTIVATE12 · Question #4
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase? There are 2 correct answers to this question.
The correct answer is C. Fit-to-standard workshop D. Configuration definition. See the full explanation below for the reasoning.
Question
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase? There are 2 correct answers to this question.
Options
- AKick-off workshop
- BIntegration prerequisites confirmation
- CFit-to-standard workshop
- DConfiguration definition
How the community answered
(50 responses)- A12% (6)
- B6% (3)
- C82% (41)