When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer. Response:
The correct answer is D. After Integration Testing. See the full explanation below for the reasoning.
Question
When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer. Response:
Options
- ABefore Integration Testing
- BDuring each Firm-up Sprint
- CAfter each Sprint
- DAfter Integration Testing
How the community answered
(43 responses)- A14% (6)
- B5% (2)
- C7% (3)
- D74% (32)