In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer.

The correct answer is B. Final testing. See the full explanation below for the reasoning.

Question

In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer.

Options

  • AScheduling project plan
  • BFinal testing
  • CInterface setup
  • DHyper care support

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    74% (17)
  • C
    13% (3)
  • D
    4% (1)