SAP
C_A1FIN_10 · Question #82
What separates the previous year's transactions from the current year's transactions in assets under construction (AuC) processing?
The correct answer is A. Transaction type. See the full explanation below for the reasoning.
Question
What separates the previous year's transactions from the current year's transactions in assets under construction (AuC) processing?
Options
- ATransaction type
- BDocument type
- CSettlement date
- DPosting date
How the community answered
(61 responses)- A70% (43)
- B8% (5)
- C16% (10)
- D5% (3)
Community Discussion
No community discussion yet for this question.