A customer is planning a large consolidation project of multiple System z servers and numerous distributed servers. Which method is appropriate to perform a capacity planning and a TCO analysis for…

The correct answer is C. Scorpion study to perform an in depth analysis of the environment. See the full explanation below for the reasoning.

Question

A customer is planning a large consolidation project of multiple System z servers and numerous distributed servers. Which method is appropriate to perform a capacity planning and a TCO analysis for the consolidation?

Options

  • ARACEv tool to perform an in depth analysis of the environment
  • BRule of thumb (ten x86 processors = 1 IFL, 3 Power CPUs = 1IFL)
  • CScorpion study to perform an in depth analysis of the environment
  • DCommercial benchmark results to estimate the hardware capacity and the BVAT for the TCO

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    83% (39)
  • D
    11% (5)