C4070-604 · Question #34

Once the sale of a System z has been made, which of the following individuals is responsible to ensure that the implementation plan is executed?

The correct answer is B. IBM or Business Partner Technical Specialist. See the full explanation below for the reasoning.

Question

Once the sale of a System z has been made, which of the following individuals is responsible to ensure that the implementation plan is executed?

Options

  • AIBM or Business Partner TDA Leader
  • BIBM or Business Partner Technical Specialist
  • CIBM Installation Planning Representative
  • DIBM or Business Partner Client Representative

How the community answered

(33 responses)
  • A
    15% (5)
  • B
    73% (24)
  • C
    6% (2)
  • D
    6% (2)