IBM
C4040-332 · Question #39
An administrator plans to migrate a PowerHA 6 cluster with AIX 7 nodes to PowerHA 7. Which migration method should be used to minimize downtime?
The correct answer is B. Rolling migration. See the full explanation below for the reasoning.
Question
An administrator plans to migrate a PowerHA 6 cluster with AIX 7 nodes to PowerHA 7. Which migration method should be used to minimize downtime?
Options
- AOffline migration
- BRolling migration
- CSnapshot migration
- DNon-disruptive migration
How the community answered
(51 responses)- A2% (1)
- B82% (42)
- C12% (6)
- D4% (2)
Community Discussion
No community discussion yet for this question.