Failure to plan for which element will have a negative impact on PowerHA cluster availability, when using virtual I/O resources on the cluster nodes?
The correct answer is C. Planning for update of Virtual I/O Servers. See the full explanation below for the reasoning.
Question
Failure to plan for which element will have a negative impact on PowerHA cluster availability, when using virtual I/O resources on the cluster nodes?
Options
- APlanning for NPIV capable SAN switches
- BPlanning for Etherchannel capable switches
- CPlanning for update of Virtual I/O Servers
- DPlanning for at least 2 virtual Ethernet adapters for each cluster network and each node
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C82% (28)
- D9% (3)
Community Discussion