A customer is running AIX and IBM i partitions on a POWER7+740 attached to a Storwize V7000 and needs both High Availability and Disaster Recovery. Which of the following pars of actions supports…

The correct answer is C. Add a second Power Systems server and Storwize V7000 in a remote location. See the full explanation below for the reasoning.

Question

A customer is running AIX and IBM i partitions on a POWER7+740 attached to a Storwize V7000 and needs both High Availability and Disaster Recovery. Which of the following pars of actions supports these requirements?

Options

  • AAdd PowerHA Express Edition to the existing server.
  • BAdd a second Power Systems server at a remote location.
  • CAdd a second Power Systems server and Storwize V7000 in a remote location.
  • DAdd a second Power Systems server and Storwize V7000 in a remote location.

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    85% (23)
  • D
    7% (2)