An audit process is currently scheduled to run with User1 as a receiver. User1 leaves the company and the Guardium administrator is asked to replace User1 with User2. How can the administrator…
The correct answer is C. Clone the current audit process, remove User1, and add User2. See the full explanation below for the reasoning.
Question
An audit process is currently scheduled to run with User1 as a receiver. User1 leaves the company and the Guardium administrator is asked to replace User1 with User2. How can the administrator achieve this?
Options
- ACreate another audit process with User2 as the receiver.
- BModify the audit process to add the User2 as the receiver.
- CClone the current audit process, remove User1, and add User2.
- DModify the audit process, delete the User1 as the receiver, and add User2 as the receiver.
How the community answered
(22 responses)- A5% (1)
- B9% (2)
- C82% (18)
- D5% (1)