IBM
C2150-606 · Question #9
A Guardium administrator installed the BUNDLE-STAP module and is monitoring the state of the install. Which state requires a database server reboot to complete the installation process?
The correct answer is B. IP-PR. The IP-PR states means that the module requires client reboot in order to complete the installation process. 01.ibm.com/support/knowledgecenter/SSMPHH_9.5.0/com.ibm.guardium95.doc/gim/topics/gim_c
Architecture and Installation
Question
A Guardium administrator installed the BUNDLE-STAP module and is monitoring the state of the install. Which state requires a database server reboot to complete the installation process?
Options
- AIP
- BIP-PR
- CFAILED
- DPENDING-UPDATE
How the community answered
(63 responses)- A6% (4)
- B79% (50)
- C3% (2)
- D11% (7)
Explanation
The IP-PR states means that the module requires client reboot in order to complete the installation process. 01.ibm.com/support/knowledgecenter/SSMPHH_9.5.0/com.ibm.guardium95.doc/gim/topics/gim_c