A Guardium administrator installed the BUNDLE-STAP module and is monitoring the state of the install. Which state requires a database server reboot to complete the installation process?

The correct answer is B. IP-PR. The IP-PR states means that the module requires client reboot in order to complete the installation process. 01.ibm.com/support/knowledgecenter/SSMPHH_9.5.0/com.ibm.guardium95.doc/gim/topics/gim_c

Architecture and Installation

Question

A Guardium administrator installed the BUNDLE-STAP module and is monitoring the state of the install. Which state requires a database server reboot to complete the installation process?

Options

  • AIP
  • BIP-PR
  • CFAILED
  • DPENDING-UPDATE

How the community answered

(63 responses)
  • A
    6% (4)
  • B
    79% (50)
  • C
    3% (2)
  • D
    11% (7)

Explanation

The IP-PR states means that the module requires client reboot in order to complete the installation process. 01.ibm.com/support/knowledgecenter/SSMPHH_9.5.0/com.ibm.guardium95.doc/gim/topics/gim_c