Which statement is true?

The correct answer is D. A full team area hierarchy can be specified in the Create Team Areas action. See the full explanation below for the reasoning.

Question

Which statement is true?

Options

  • ATeam areas cannot be created a project area initialization time.
  • BOnly one team area can be created a project area initialization time.
  • CA Create Team Area action is part of the default project area initialization actions.
  • DA full team area hierarchy can be specified in the Create Team Areas action.

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    10% (5)
  • C
    2% (1)
  • D
    84% (42)