A work item appears in a plan when which two conditions are met? (Choose two.)

The correct answer is A. The Filed Against field has the work item category linked to the team area that owns the plan. D. The Planned For field in the work item matches the Iteration field of the plan. See the full explanation below for the reasoning.

Question

A work item appears in a plan when which two conditions are met? (Choose two.)

Options

  • AThe Filed Against field has the work item category linked to the team area that owns the plan.
  • BThe Due Date field of the work item is on or before the end date of the plan.
  • CThe work item is assigned to a member of the team that owns the plan.
  • DThe Planned For field in the work item matches the Iteration field of the plan.
  • EThe work item is created by a member of the team area that owns the plan.

How the community answered

(40 responses)
  • A
    83% (33)
  • B
    3% (1)
  • C
    10% (4)
  • E
    5% (2)