nerdexam
IBM

C2140-820 · Question #48

An organization uses the Formal Project Management process template for a project. Some work items in the Gantt chart view of an iteration plan for the project are shown in red. What does red…

The correct answer is C. on the critical path. See the full explanation below for the reasoning.

Question

An organization uses the Formal Project Management process template for a project. Some work items in the Gantt chart view of an iteration plan for the project are shown in red. What does red indicate?

Options

  • Ahigh severity
  • Bhigh priority
  • Con the critical path
  • Dunassigned

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    10% (4)
  • C
    83% (34)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full C2140-820 Practice