An organization uses the Formal Project Management process template for a project. Some work items in the Gantt chart view of an iteration plan for the project are shown in red. What does red…
The correct answer is C. on the critical path. See the full explanation below for the reasoning.
Question
An organization uses the Formal Project Management process template for a project. Some work items in the Gantt chart view of an iteration plan for the project are shown in red. What does red indicate?
Options
- Ahigh severity
- Bhigh priority
- Con the critical path
- Dunassigned
How the community answered
(41 responses)- A5% (2)
- B10% (4)
- C83% (34)
- D2% (1)