Question

A customer expects a work item with an appropriate "Planned for" attribute to show on a team's iteration plan, but the work item is missing from the plan view. What is the most likely reason?

Options

  • AThe work item's owner is unassigned.
  • BThe work item's owner is not part of the team owning the plan.
  • CThe work item's Filed Against category is not associated to the team owning the plan.
  • DThe work item's due date is set to a date after the iteration's end date.