You are using the Scrum process template for a project. Story points on a work item for this project are a measure of the workload in units of what?
The correct answer is B. complexity. See the full explanation below for the reasoning.
Question
You are using the Scrum process template for a project. Story points on a work item for this project are a measure of the workload in units of what?
Options
- Atime
- Bcomplexity
- Csignificance
- Dseverity