IBM
C2140-820 · Question #29
An organization follows the Scrum process template to build a product with multiple releases. What plan type should they use to track the major goals for a specific product release?
The correct answer is B. Release Backlog. See the full explanation below for the reasoning.
Question
An organization follows the Scrum process template to build a product with multiple releases. What plan type should they use to track the major goals for a specific product release?
Options
- AProduct Backlog
- BRelease Backlog
- CIteration Plan
- DProject Plan
How the community answered
(22 responses)- A5% (1)
- B77% (17)
- C9% (2)
- D9% (2)
Community Discussion