An organization follows the Scrum process template to build a product with multiple releases. What plan type should they use to track the major goals for a specific product release?

The correct answer is B. Release Backlog. See the full explanation below for the reasoning.

Question

An organization follows the Scrum process template to build a product with multiple releases. What plan type should they use to track the major goals for a specific product release?

Options

  • AProduct Backlog
  • BRelease Backlog
  • CIteration Plan
  • DProject Plan