Which two statements are true when reporting actual labor? (Choose two.)

The correct answer is C. Labors from different labor contracts can be added at the same time. E. The start date for each labor line item can be different from the start date of the work order. See the full explanation below for the reasoning.

Question

Which two statements are true when reporting actual labor? (Choose two.)

Options

  • AWork order must have planned labor.
  • BIn order to input actuals, a work order cannot be in COMP status.
  • CLabors from different labor contracts can be added at the same time.
  • DThe Planned Labor can be applied to Actuals from the Select Action menu.
  • EThe start date for each labor line item can be different from the start date of the work order.

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    70% (23)
  • D
    18% (6)

Community Discussion