nerdexam
IBM

C2010-595 · Question #53

Which step is required to apply a calendar to an asset in IBM Maximo Asset Management VV7.5?

The correct answer is A. on the asset record, enter the calendar name in the Calendar field. See the full explanation below for the reasoning.

Question

Which step is required to apply a calendar to an asset in IBM Maximo Asset Management VV7.5?

Options

  • Aon the asset record, enter the calendar name in the Calendar field
  • Bfrom the Select Action menu of the Assets application, choose Apply Calendar
  • Cfrom the Select Action menu of the Calendars application, choose the Add/Modify Assets option
  • Dfrom the Select Action menu of the Assets application, choose Manage Downtime History and

How the community answered

(54 responses)
  • A
    78% (42)
  • B
    4% (2)
  • C
    7% (4)
  • D
    11% (6)

Community Discussion

No community discussion yet for this question.

Full C2010-595 Practice