Which step is required to apply a calendar to an asset in IBM Maximo Asset Management VV7.5?
The correct answer is A. on the asset record, enter the calendar name in the Calendar field. See the full explanation below for the reasoning.
Question
Which step is required to apply a calendar to an asset in IBM Maximo Asset Management VV7.5?
Options
- Aon the asset record, enter the calendar name in the Calendar field
- Bfrom the Select Action menu of the Assets application, choose Apply Calendar
- Cfrom the Select Action menu of the Calendars application, choose the Add/Modify Assets option
- Dfrom the Select Action menu of the Assets application, choose Manage Downtime History and
How the community answered
(54 responses)- A78% (42)
- B4% (2)
- C7% (4)
- D11% (6)