C2010-595 · Question #46

Which statement is true when trying to generate a forecast on a preventive maintenance (PM) record?

The correct answer is B. The PM must have a due date. See the full explanation below for the reasoning.

Question

Which statement is true when trying to generate a forecast on a preventive maintenance (PM) record?

Options

  • AThe PM must be inactive.
  • BThe PM must have a due date.
  • CA forecast must already exist for this PM.
  • DThe Forecast field must not be checked for the PM.

How the community answered

(30 responses)
  • A
    17% (5)
  • B
    70% (21)
  • C
    3% (1)
  • D
    10% (3)