Which statement is true when trying to generate a forecast on a preventive maintenance (PM) record?
The correct answer is B. The PM must have a due date. See the full explanation below for the reasoning.
Question
Which statement is true when trying to generate a forecast on a preventive maintenance (PM) record?
Options
- AThe PM must be inactive.
- BThe PM must have a due date.
- CA forecast must already exist for this PM.
- DThe Forecast field must not be checked for the PM.
How the community answered
(30 responses)- A17% (5)
- B70% (21)
- C3% (1)
- D10% (3)