The actual start date on a service request is populated by the system when the record is changed to which status?

The correct answer is C. INPROG. See the full explanation below for the reasoning.

Question

The actual start date on a service request is populated by the system when the record is changed to which status?

Options

  • ANEW
  • BDRAFT
  • CINPROG
  • DQUEUED

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    74% (17)
  • D
    17% (4)