How is the description field updated on a work order when a route is applied?

The correct answer is B. If the route stop has a description, the route description becomes the work order description. See the full explanation below for the reasoning.

Question

How is the description field updated on a work order when a route is applied?

Options

  • AIf the route stop has no description, the first job plan task becomes the description.
  • BIf the route stop has a description, the route description becomes the work order description.
  • CIf the route stop has a description and refers to an asset, the route description becomes the asset
  • DIf the route stop has no description and refers to an asset, the route description becomes the

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    83% (33)
  • C
    10% (4)
  • D
    3% (1)