To schedule labor using Assignment Manager, what must be specified on the person record in the People Application?
The correct answer is D. a calendar and a shift. See the full explanation below for the reasoning.
Question
To schedule labor using Assignment Manager, what must be specified on the person record in the People Application?
Options
- Anothing
- Ba shift only
- Ca calendar only
- Da calendar and a shift
How the community answered
(37 responses)- A5% (2)
- B14% (5)
- C3% (1)
- D78% (29)