C2010-595 · Question #3

What if the projected forecast date for a preventive maintenance (PM) record occurs in an inactive season?

The correct answer is D. The PM record is forecasted on the earliest date in the next active season. See the full explanation below for the reasoning.

Question

What if the projected forecast date for a preventive maintenance (PM) record occurs in an inactive season?

Options

  • AThe active season dates should be modified.
  • BThe inactive season dates should be modified.
  • CThe PM record is forecasted on the latest date in the next active season.
  • DThe PM record is forecasted on the earliest date in the next active season.

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    7% (2)
  • D
    85% (23)