C2010-595 · Question #165

What is required to generate a forecast for an existing preventive maintenance record?

The correct answer is A. Estimated next due date. See the full explanation below for the reasoning.

Question

What is required to generate a forecast for an existing preventive maintenance record?

Options

  • AEstimated next due date
  • BLast work order start date
  • CLast work order generation date
  • DLast work order completion date

How the community answered

(41 responses)
  • A
    83% (34)
  • B
    2% (1)
  • C
    5% (2)
  • D
    10% (4)

Community Discussion

No community discussion yet for this question.