C2010-595 · Question #140

Which two selections are valid to create associated preventive maintenance (PM) records from a master PM?

The correct answer is B. Item's assets D. Item's locations. See the full explanation below for the reasoning.

Question

Which two selections are valid to create associated preventive maintenance (PM) records from a master PM?

Options

  • APM records
  • BItem's assets
  • CClassification
  • DItem's locations
  • EItem's storerooms

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    79% (34)
  • C
    12% (5)
  • E
    2% (1)

Community Discussion

No community discussion yet for this question.