Question
To fully utilize a safety plan, what is the proper sequence to create the necessary records?
Options
- ACreate the lock outs, create the asset, create the work order, and then create the safety plan
- BCreate the hazard, create the precaution, create the safety plan, and then create the work order
- CCreate the hazardous material, create the safety plan, create the precautions, and then create the
- DCreate the asset, create the hazards for the asset, create the safety plan, create the tag outs, and