Which statement is true about a master preventive maintenance (PM) record?
The correct answer is A. A master PM record does not generate work orders. See the full explanation below for the reasoning.
Question
Which statement is true about a master preventive maintenance (PM) record?
Options
- AA master PM record does not generate work orders.
- BAssociated PM records cannot be created from master PM records.
- CA master PM record generates work orders like any other PM records.
- DAssociations between existing PM records and a master PM record cannot be made
How the community answered
(25 responses)- A72% (18)
- B8% (2)
- C4% (1)
- D16% (4)
Community Discussion
No community discussion yet for this question.