C2010-555 · Question #34

A planner has a high priority work order which is going to consume an item with limited availability and wants to ensure that the item is dedicated to this work order. What type of reservation…

The correct answer is B. HARD. https://www-01.ibm.com/support/docview.wss?uid=swg21683654

Planning and Architecture

Question

A planner has a high priority work order which is going to consume an item with limited availability and wants to ensure that the item is dedicated to this work order. What type of reservation should the planner use?

Options

  • ASOFT
  • BHARD
  • CAPSOFT
  • DBACKORDER

How the community answered

(14 responses)
  • A
    14% (2)
  • B
    71% (10)
  • C
    7% (1)
  • D
    7% (1)

Explanation

https://www-01.ibm.com/support/docview.wss?uid=swg21683654

Topics

#HARD reservation#inventory reservation#material planning#work order priority