Question
A company recently had to do a massive overhaul of a pump asset. The planner has to enter hundreds of tasks, sequence those tasks, and identify the labor, material, services and tools used on each task. The planner knows that this work will occur again as the company has numerous pumps of the same type. What must the planner do so that the work plan does not have to be re- entered?
Options
- ACreate a Job Plan
- BCreate a follow-up work order
- CAcquire an extended warranty for the overall work
- DUse the Create Job Plan from Work Plan functionality
Unlock C2010-555 to see the answer
You've previewed enough free C2010-555 questions. Unlock C2010-555 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.