C2010-555 · Question #154

A company has acquired a contract for an asset covering labor, materials and tools. What must be created to capture this information?

The correct answer is A. A Master Contract. r_mam_mod_contracts.html Exam Code: C2010 IBM Maximo Asset Management v7.6 Functional Analyst Version: 20.061 Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of…

Procurement Management

Question

A company has acquired a contract for an asset covering labor, materials and tools. What must be created to capture this information?

Options

  • AA Master Contract
  • BA Warranty Contract
  • CA Purchase Contract
  • DA Labor Rate Contract

How the community answered

(66 responses)
  • A
    83% (55)
  • B
    5% (3)
  • C
    3% (2)
  • D
    9% (6)

Explanation

r_mam_mod_contracts.html Exam Code: C2010 IBM Maximo Asset Management v7.6 Functional Analyst Version: 20.061 Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#Master Contract#contract types#labor materials tools#contract management