The correct answer is C. Request for quotation lines must be awarded to a vendor.. See the full explanation below for the reasoning.
Question
A user has created a request for quotation and sent it to vendors. After receiving the responses from the vendors, the user will need to create a purchase order. What action must be performed before a purchase order can be created?
Options
- APurchase requisitions must first be created.
- BStatus of the request for quotation must be APPR.
- CRequest for quotation lines must be awarded to a vendor.
- DVendor quotation receipt transactions must be completed.
Community Discussion