C2010-555 · Question #122
Which statement is true about routes?
The correct answer is A. A route can only be applied to a work order by a PM. See the full explanation below for the reasoning.
Question
Which statement is true about routes?
Options
- AA route can only be applied to a work order by a PM.
- BA route's sequence numbers are fixed after it is activated.
- CA route can create work orders for locations or assets, not both.
- DRoute Stops that become work order tasks cannot have job plans.
How the community answered
(42 responses)- A76% (32)
- B5% (2)
- C12% (5)
- D7% (3)