C2010-555 · Question #121
A company is using Process Flow Control and wants to change the default values for Flow Start and Flow Complete statuses. Where can these values be configured?
The correct answer is B. Work Type settings. See the full explanation below for the reasoning.
Question
A company is using Process Flow Control and wants to change the default values for Flow Start and Flow Complete statuses. Where can these values be configured?
Options
- ASystem Properties
- BWork Type settings
- CWOSTATUS Domain
- DChange Work Order Options action
How the community answered
(36 responses)- A3% (1)
- B81% (29)
- C8% (3)
- D8% (3)