IBM
C2010-505 · Question #15
A bank is currently in negotiations to renew their multiple contracts with a software vendor with overreaching terms and conditions. There are no contract records in IBM SmartCloud Control Desk for…
The correct answer is A. Master Contract. See the full explanation below for the reasoning.
Question
A bank is currently in negotiations to renew their multiple contracts with a software vendor with overreaching terms and conditions. There are no contract records in IBM SmartCloud Control Desk for the new agreement. What is the best contract for the contracts compliance manager to create?
Options
- AMaster Contract
- BSoftware Contract
- CWarranty Contract
- DPurchase Contract
How the community answered
(36 responses)- A75% (27)
- B3% (1)
- C8% (3)
- D14% (5)
Community Discussion