C2010-505 · Question #135

What must be done to an item on the POLine before a license can automatically be created from a purchase order?

The correct answer is C. It must be linked to a software product from the Software Catalog. See the full explanation below for the reasoning.

Question

What must be done to an item on the POLine before a license can automatically be created from a purchase order?

Options

  • AIt must be linked to a rotating asset.
  • BIt must be linked to a deployed software asset
  • CIt must be linked to a software product from the Software Catalog.
  • DIt must be linked to an existing license so that the capacity can be incremented.

How the community answered

(34 responses)
  • A
    21% (7)
  • B
    6% (2)
  • C
    71% (24)
  • D
    3% (1)