Which two types of records can be associated with a calendar and shift?(Choose two)
The correct answer is C. Assets D. Locations. See the full explanation below for the reasoning.
Question
Which two types of records can be associated with a calendar and shift?(Choose two)
Options
- ATools
- BItems
- CAssets
- DLocations
- EAsset Templates
How the community answered
(37 responses)- A16% (6)
- B3% (1)
- C73% (27)
- E8% (3)