What is an activity of the process Specify information requirements?
The correct answer is C. validating and approving specifications. Validating and approving specifications (C) is correct because the core purpose of the "Specify information requirements" process is to define, document, and confirm what information the business needs - culminating in validated, approved specs that can guide development or…
Question
What is an activity of the process Specify information requirements?
Options
- Adecision-making about the execution of changes
- Bidentifying IT-solutions
- Cvalidating and approving specifications
How the community answered
(14 responses)- A14% (2)
- B7% (1)
- C79% (11)
Explanation
Validating and approving specifications (C) is correct because the core purpose of the "Specify information requirements" process is to define, document, and confirm what information the business needs - culminating in validated, approved specs that can guide development or procurement.
Option A (decision-making about executing changes) belongs to a change management process, not requirements specification - it concerns whether and how to implement a change, not what the requirements are.
Option B (identifying IT solutions) belongs to a design or architecture process; specifying requirements deliberately avoids prescribing solutions so that needs are captured independently of technology.
Memory tip: Think of "Specify" as the what, not the how or whether. Validating and approving specs is the natural endpoint of defining requirements - you write them, then you sign them off. Anything about choosing technology (B) or greenlighting changes (A) happens after requirements are locked.