Question

How does Problem Management work with Change Management?

Options

  • ABy installing changes to fix problems
  • BBy negotiating with Incident Management for changes in IT for Problem resolution
  • CBy issuing RFCs for permanent solutions
  • DBy working with users to change their IT configurations