Which process is responsible for frequently occurring changes where risk and cost are low?
The correct answer is B. Request Fulfillment. See the full explanation below for the reasoning.
Question
Which process is responsible for frequently occurring changes where risk and cost are low?
Options
- AIncident Management
- BRequest Fulfillment
- CRelease and Deployment Management
- DAccess management
How the community answered
(42 responses)- A5% (2)
- B83% (35)
- C2% (1)
- D10% (4)