BH0-012 · Question #168

Match the following activities with the Deming Cycle stages 1. Monitor, Measure and Review 2. Continual Improvement 3. Implement Initiatives 4. Plan for Improvement

The correct answer is C. 4 Plan, 3 Do, 1 Check, 2 Act. See the full explanation below for the reasoning.

Question

Match the following activities with the Deming Cycle stages 1. Monitor, Measure and Review 2. Continual Improvement 3. Implement Initiatives 4. Plan for Improvement

Options

  • A1 Plan, 2 Do, 3 Check, 4 Act
  • B3 Plan, 2 Do, 4 Check, 1 Act
  • C4 Plan, 3 Do, 1 Check, 2 Act
  • D2 Plan, 3 Do, 4 Check, 1 Act

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    7% (1)
  • C
    86% (12)

Community Discussion

No community discussion yet for this question.