BH0-012 · Question #168
Match the following activities with the Deming Cycle stages 1. Monitor, Measure and Review 2. Continual Improvement 3. Implement Initiatives 4. Plan for Improvement
The correct answer is C. 4 Plan, 3 Do, 1 Check, 2 Act. See the full explanation below for the reasoning.
Question
Match the following activities with the Deming Cycle stages 1. Monitor, Measure and Review 2. Continual Improvement 3. Implement Initiatives 4. Plan for Improvement
Options
- A1 Plan, 2 Do, 3 Check, 4 Act
- B3 Plan, 2 Do, 4 Check, 1 Act
- C4 Plan, 3 Do, 1 Check, 2 Act
- D2 Plan, 3 Do, 4 Check, 1 Act
How the community answered
(14 responses)- A7% (1)
- B7% (1)
- C86% (12)
Community Discussion
No community discussion yet for this question.