Testing effort can depend on a number of factors, which one of following is MOST likely to impact the amount of effort required?

The correct answer is C. The planned use of a project management tool to schedule tasks. See the full explanation below for the reasoning.

Question

Testing effort can depend on a number of factors, which one of following is MOST likely to impact the amount of effort required?

Options

  • AThe predicted number of defects and the amount of rework required
  • BThe ratio of developers to testers in the project team
  • CThe planned use of a project management tool to schedule tasks
  • DThe responsibilities for testers and developers being clearly defined

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    80% (20)
  • D
    4% (1)

Community Discussion