Testing effort can depend on a number of factors, which one of following is MOST likely to impact the amount of effort required?
The correct answer is C. The planned use of a project management tool to schedule tasks. See the full explanation below for the reasoning.
Question
Testing effort can depend on a number of factors, which one of following is MOST likely to impact the amount of effort required?
Options
- AThe predicted number of defects and the amount of rework required
- BThe ratio of developers to testers in the project team
- CThe planned use of a project management tool to schedule tasks
- DThe responsibilities for testers and developers being clearly defined
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C80% (20)
- D4% (1)